This Spring (2018) we have had the opportunity to make some great improvements to the property!

 

The S dock rebuild is underway. We are making good progress so far. As we rebuild this dock we are running new plumbing so we can connect it to the pump out system and replacing the old power pedestals.

 

O-Dock seawall is almost complete. The cap is scheduled to be poured on 4/19/2018